Construction & Contracting// definition

Deferred submittals: the items the register has to hold open

In short

A deferred submittal is a portion of the design the permit authority agrees may be submitted after the main permit is issued — usually a delegated-design package sealed by a specialty contractor's engineer. It differs from an ordinary submittal in 3 fields: the event that opens it, an external reviewer whose clock your contract does not govern, and a date back-calculated from installation.

Key takeaways

  • A deferred item is an obligation with a later trigger, not one nobody has got round to yet.
  • Delegated design is about who produces the design; deferred is about when it reaches the authority.
  • The external reviewer's queue is not governed by your subcontract, so its duration has to be asked for.
  • Back-calculate from installation: the buyout that fires the trigger is the date that actually binds.
  • A register with no not-yet-openable state files these under 'not started' and loses them.

A deferred submittal is a portion of the design that the permit authority has agreed may be submitted after the main permit is issued, rather than with the application. In practice it is almost always a delegated-design package: the specialty contractor's engineer produces and seals it, the design professional in responsible charge reviews it against the base design, and it goes to the authority for approval before that work is installed.

The two terms get used interchangeably and mean different things. Delegated design is about who produces the design; deferred is about when it reaches the authority. A package can be delegated and not deferred, and only one of the two puts a reviewer outside your contract on the critical path.

Deferred, delegated and long-lead are three different states

StateWho produces the designWho reviews itWhat opens the clock
Ordinary submittalThe manufacturer or trade contractorThe design team, inside the contract's review periodAward of the package
Delegated designA specialty engineer engaged by the trade contractor, who seals itThe design professional, against the base designAward, plus release of the base design it depends on
Deferred submittalUsually a specialty engineer, sealedThe design professional, then the authority having jurisdictionAn agreement at permit that this item comes later
Long-lead itemNot a design questionNobody, in review termsProcurement. It belongs on the buyout schedule.
Four things a register is asked to hold, and what distinguishes them

Typical delegated packages are those where fabrication engineering sits with the fabricator: steel connections, precast concrete, trusses, curtain wall, metal stairs, fire sprinkler layout, seismic bracing for MEP services. Most arrive as a small sheet set numbered by the specialty engineer rather than the consultant, so an index built on the consultant's convention loses them — which is why the title block is the metadata layer of a sheet set matters as soon as these land.

The fields a deferred row needs that an ordinary one does not

  • The trigger event, named. Not a date — an event: award of the package, release of a base-design sheet, a client decision. Until it fires no submission date exists, and a blank date sorts to the bottom of every view.
  • The external reviewer, and their queue. The design team's review period is a contract term. The authority's plan-review queue is not, so ask for its duration at pre-application.
  • The sealing engineer, and where they are licensed. The seal must be valid in the project's jurisdiction — a buyout question that has scuppered packages awarded on price alone.
  • A not-yet-openable state, distinct from not started. Collapsing the two is the single reason deferred items vanish from registers.
  • The base-design dependency. If the base design is revised after the package was designed against it, somebody must tell the specialty engineer which sheets moved — the job a revision comparison flagging hundreds of meaningless changes exists to do.

Why 'not started' is where these items go to die

A register earns its keep by sorting on the latest safe submission date. A deferred row has no such date until its trigger fires, so it sorts to the bottom, sorts as a blank, or drops out of the open-items filter. Nobody decided to ignore it. The view did.

An obligation with a trigger nobody owns keeps costing money quietly, the same shape as plant that stays on hire after it leaves the yard — the failure in still invoiced for plant that left site. The record exists and no one is accountable for the date on it.

The approval requirement is jurisdictional, so read your own

Deferred submittals exist because the building code as adopted in your jurisdiction provides for them, and provisions differ on which items may be deferred, who reviews before the authority sees them, and whether the work may be installed before approval. Ask the authority having jurisdiction at pre-application and get the answer in writing rather than carrying last project's across a border. This describes practice, not legal advice.

One question sits outside this page: when a sealed delegated design conflicts with the base drawings or the specification, which governs is a contract matter with a per-project answer, set out in order of precedence when the drawing and the spec conflict.

What a document system should actually do with a deferred row

  1. Extract candidates from the specification and flag them for a human rather than classifying automatically — the boundary drawn in turning a spec book into a submittal list.
  2. Record the trigger as a relationship to another object — a buyout package, a permit milestone, a base-design sheet — so it fires without anyone remembering to fire it.
  3. Hold the external review duration as a separate, explicitly sourced field, and show on the row where the number came from.
  4. Compute the trigger deadline backwards from installation and surface it on the procurement report, not only the submittal log.
  5. Alert on the trigger date, not the submission date. Once a submission date is late, the sequence has already failed.

A deferred item is not an obligation nobody has got round to. It is an obligation waiting on an event, and events need owners.

How the rest of the register gets built is separate work, set out in the submittal register as a generated artefact. Building the register, its trigger relationships and the review queue over them is scoped product work of the kind we run under MVP and product builds. The rest of this silo sits under drawings, specs and document intelligence, inside our construction work.

Frequently asked questions

Short answers to the follow-ups this page tends to raise.

What is a deferred submittal?

It is a portion of the design the permit authority has agreed may be submitted after the main permit is issued rather than with the application. It usually arrives as a sealed delegated-design package, is reviewed by the design professional in responsible charge, and goes to the authority for approval before that work is installed.

What is the difference between a deferred submittal and a delegated design submittal?

Delegated design describes who produces the design — a specialty engineer working for the trade contractor, who seals it. Deferred describes when it reaches the permit authority. Most deferred items are delegated, but a delegated package included in the original permit application is not deferred.

Who is responsible for deferred submittals?

The contractor procures and submits them, the specialty engineer designs and seals them, and the design professional in responsible charge reviews them against the base design before they reach the authority. The exact division varies by jurisdiction and by contract, so confirm both.

When does the clock start on a deferred submittal?

At the trigger event — usually award of the package or release of the base design it depends on, not contract award. Because the sequence runs engineer, design professional, authority, fabrication and delivery, the binding date can sit 20 weeks or more before installation.

  • submittals
  • delegated design
  • specifications
  • project controls
// shipped work

The work behind this page

Builds from our portfolio that this page draws on.

Read next

Working on something in this space?

Tell us where you are in a sentence or two. We'll tell you honestly whether we're the right team, and what a sensible first slice of the work looks like.

Start the conversation